Capital investment
Rehabilitation work at the La Guaira terminal has reached 70% completion in its external areas, while work inside the facility stands at 40%, Governor José Alejandro Terán said. The update indicates uneven progress across the project, with interior work trailing the exterior phase. No completion timetable, budget, contractor information or operational milestones were provided, leaving the remaining execution schedule and the terminal’s eventual service impact unclear.